A House – Update XXXII – Attic Access

With the ceiling sealed in and still needing to get insulation in the attic, I also needed a way to provide an access portal into the attic. I figured having it above the closet of our bedroom was probably best, so that I could stand on top of it to be able to more easily get into the attic without having to have a taller ladder to reach the greater than 11 foot ceiling height.

After some planning and obtaining some supplies, I delved on in…

This is the panel I chose. Besides being above the closet, I wanted to use one of the half-panels so I could more easily remove and install the panel without assistance:

Ceiling Panel to Put Attic Access In

Here it is removed. Before removing it, I first had to remove another small panel so I could get into the attic and mark out lines where the trusses ran along the access panel, which would help me know exactly where I would need to cut:

Ceiling Panel Removed

Once the panel was down, I drew the cut lines that would make the access door. The plan was to have one side of the door be the original side of the panel and close onto a truss and cover half way, thus requiring only three cuts. The opposite side (shown top here) would lay half way on the other truss, allowing the panel to be re-attached to the truss and for the door to cover the other, exposed half of that truss when closed:

Cut Lines Drawn on Ceiling Panel

And here is the cut panel:

Attic Access Door Cut Out of Ceiling Panel

And then back into place in the ceiling:

Cut Ceiling Panel Back in Place

Here is the view from the attic, showing the cross pieces in place. The cross piece that was to hold the door hinges I put flush with the ceiling panel cut, and the other side, where the latches would be, I put exposing half of the cross piece, which would allow for that side of the closed door to cover that half of the cross piece:

Attic Access View from Attic

Then, it was on to making the door…

Here are the door frame pieces. They needed to be cut to length so the hinge side would be flush with that edge, and the other three sides would show about one inch of panel, which are what would cover the exposed halves of the trusses and cross pieces when closed, plus a little gap to keep the door frame from hitting a truss or cross piece when actually closing the door:

Attic Access Door Frame Pieces

These are the pieces made into the door frame:

Attic Access Door Frame

And then installed on the door:

Attic Access Door Frame on Door Panel

Here, the door hardware is installed — two hinges and two bolt latches:

Attic Access Door Hardware Installed

And close-ups of each:

Attic Access Door Bolt Latches
Attic Access Door Hinges

This is the fancy way I held the door in place to attach the hinges to the ceiling and cross piece: 🙂

Attaching Attic Access Door Hinges to Ceiling

And here the door is closed and latched into place! One side of the bolt latch on the door didn’t have a door frame into which to put screws, so the ends of the screws were sticking out and preventing the door from completely closing; so I drilled out little holes into the cross piece where the ends of the screws would fit into:

Attic Access Door Bolt Latches Latched

And here is the original ceiling panel showing the new attic access door installed:

Attic Access Door Installed

And with it open:

Open Attic Access Door

From the back side:

Open Attic Access Door Back Side

And front side:

Open Attic Access Door Front Side

I was amazed it actually worked. It was almost anti-climactic in that there was no “drama” with it, which there usually is in my building projects. 🙂 But, it was nice to have it work out as well as it appears to have worked.

We’re thankful as always to the Lord for granting the provisions and continued progress on the house, and I’m thankful to Him for the idea and plans for making this bit of the project seem to work successfully.

— David

A House – Update XXXI – External Wall Insulation

With the wood-burning stove in place, and the ceiling panels all up, the last major piece of the house-heating puzzle was the rest of the external wall insulation. We had already done the bedroom insulation some time back, but now it was time to complete the other rooms.

First, I went around and stuffed insulation in all of the door frame gaps using a shim:

Door Frame Insulation

And then I started working my way around the house, beginning with the great room living room:

Great Room Living Room Wall Insulation

Then behind the cook stove and into the kitchen. I also took the heat barrier we had been using for our barn stove and put it behind the house one:

Great Room Kitchen Wall Insulation & Heat Barrier Behind Wood-Burning Cook Stove

Through the rest of the kitchen:

More Great Room Kitchen Wall Insulation

And finally in the library:

Library Wall Insulation

And there it was! Ready for guests!

And here is a picture from outside showing the lamps and candles lit in the house for the first time we had the group over for a community meeting on a cold night!

First Cold Weather Community Meeting in Our House After House External Wall Insulation From Outside

And from inside with the camera flash before everyone got there:

First Cold Weather Community Meeting in Our House After House External Wall Insulation

Once again, we are most grateful to the Lord for supplying the resources for continuing the house, to those out there who have helped with them, and we are very thankful and excited to be able to finally host the group, and hopefully in a bit of comfort. Last year, we had to cancel some meetings because the community center stove pipe is rusted through, so we’re glad we can now meet once again, to sing praises to God and learn about the Lord Christ, in unity together, we pray for His glory, even in colder weather!

May He grant us the heat of His charity in our hearts!

— David

A House – Update XXX – External Siding – Update II

With the upper north siding of the house complete, in between other house projects, like the ceiling and wood-burning stove, I started working on the upper east side siding. Once again, I’m using cedar fence slats, which are relatively inexpensive, and ideally hearty, not requiring paint (although we’re putting wood protector on), fastening them with tan 2 1/2 inch deck screws.

Sue helped me put up the tar paper:

House Upper East Siding Tar Paper

And here are some of the window frames in place:

Upper East Window Frames

Our cat, William, scales the ladder at will, and often joins me on the porch roof:

William Our Cat on the Porch Roof

Here’s the siding about half way up:

Upper East Siding Half Way Done

And almost done:

Upper East Siding Mostly Done

And then complete!

Upper East Siding Complete

With the full view here, and the last of the caulking still fresh:

Full View of House Upper East Siding

We thank the Lord once again for providing the resources to keep working on the house! Upper south side is next, which if God wills, I hope to have done before spring rains.

— David

A House – Update XXIX – Inside Ceiling Complete

With the wood-burning cook stove now in place, it was time to get the rest of the ceiling done!

Here, a couple of the fellows came by to help:

Fellowship Men Helping Put Up Corner Ceiling Panel

And we finished the rest of the ceiling! This is between the great room and bedroom/bathroom:

Great Room/Bathroom Final Ceiling Panels in Place

And the north west corner:

Great Room Final Panels Installed

And the north east corner:

More Great Room Final Panels Installed

We’re always very grateful to the Lord for granting continued provisions and progress on the house, to those who are helping fund that, and thanks to the guys for the help in finishing up the ceiling!

On to external wall insulation!…..

— David

A House – Update XXVIII – Wood-Burning Cook Stove

All along we have planned for our main sources of heat, for warmth and cooking, for the house to be wood burning stoves. Graciously, both Sue and my parents have been very supportive of us in our living out here, and in one of the ways from one of our parent sets was an offer to buy our cook stove for us. Wow, what a very nice gift! After much research by Sue, we chose a Kitchen Queen 380.

It has been sitting in the house for quite some time now, but with the ceiling almost complete and winter getting close, it was time for me to get to work getting it installed. And here is the process!

Here is the external pipe base installed in the attic:

Stove Pipe Base in Attic

And the back and sides of an insulation barrier. Based on a video I saw on the web, I chose to just put up OSB around it to keep out foreign matter. The front piece, not shown installed, was installed next, which had a little gap at the top to allow for air flow (which I’ll mention more about below with the starter section):

Stove Pipe Insulation Shield

Here is the base installed from inside:

Stove Pipe Base Installed

And something someone left up there. I suppose I should go retrieve it. 🙂 :

Peering Through the Stove Pipe Base

Next was to cut the hole in the roof. Needing to find the center of the hole, and not having a plumb bob, I used a tape measure on a string:

Tape Measure Plumb Bob

And here is the hole drilled:

Looking Up Tape Measure Plumb Bob

The external stove pipe requires two inches of spacing from combustible material, so I drew the circle appropriately:

Roof Stove Pipe Cutting Circle Drawn

And cut out the metal using tin snips:

Cutting Roofing Metal for Stove Pipe

And then used the jig saw to cut through the roof wood:

Roof Stove Pipe Hole Cut

And here is the roof hole ready:

Stove Pipe Base Form Roof Hole

The external stove pipe is held in place with a collar, so I needed to further prepare the roof metal to receive the collar:

Metal Roof Ridge Cut Out & Side Cuts

And I had to cut the collar piece to form to be able to slide into place:

Stove Pipe Collar Cut to Form

And here is the collar in place and caulked:

Stove Pipe Collar in Place & Caulked

Something needed to be done to cover the hole in the ridge left by the circle cut, and so I took a piece of left-over collar flashing, bent it and placed it, and caulked it in place:

Metal Roofing Ridge Hole Cover in Place & Caulked

And here is another view of the collar installed:

Another View of Stove Pipe Collar

After getting the collar in place, we had some storms heading through, so I duct-taped a plastic bag to the collar and put a step stone on top, which actually ended up working, even through a severe storm we had which knocked over one of our fruit trees:

Step Stone Covering Stove Collar in Roof Opening

Continuing on to the actual external stove pipe itself, because I’ve worked with it before, and because the base, cap, and collars come in a kit, I went with triple wall for the external pipe; and here are the two main pieces snapped together. I think I calculated I needed seven feet total (it needs to be high enough so it is far enough away from the roof so as to not be disturbed by roof turbulence), and to make it easy, went with two four-foot sections:

Assembled Triple Wall Stove Pipe

Originally, I was going to skip using the starter piece, because it is very expensive and I thought not really needed for pipe installation; but after doing further research, I discovered the holes in it actually filter air up between the walls of the piping to help keep it cool, so I thought that might be important; and so, we purchased it, and here is a stock photo of it:

Triple Wall Attic Starter Piece

I also added some wire mesh to help keep the birds out of the stove pipe cap:

Bird Nest Wire in Stove Cap

With this much pipe in the air, I figured I needed to secure it to the roof with guy wires, and I thought I would use plumber’s tape to make a “collar” on top, fastened with self-tapping screws:

Guy Wire Holder Installed on Stove Pipe

And here are the guy wires attached to the collar:

Stove Pipe Guy Wires Attached

With the stove pipe ready, and the starter piece attached too, I hauled it up to the roof and placed it in the collar, with Sue in the house telling me when the starter piece was set into the base hole. Then Sue joined me on the roof to continue with the installation, and William our cat thought he would join us too (he’s really good at scaling the ladder and hopping up onto the porch roof now — here, I think I helped him get up on the upper roof):

Triple Wall Stove Pipe Place in Roof Hole

For attaching the guy wires to the roof, I used eye hooks which I tried to make sure got screwed into a truss to hopefully secure them more strongly. And I added adjustable hooks for future changes to guy-wire tension as might be needed:

Stove Pipe Guy Wires Attached to Roof

Here Sue is helping level the pipe:

Leveling the Triple Wall Stove Pipe

And here it is originally in place:

Triple Wall Stove Pipe in Place

In tightening down the guy wires, the tension bolt on the plumber’s-tape collar pulled through the plumber’s tape. Hmmmm…hadn’t seen that one coming:

Guy Wire Stove Pipe Holder Broken

So I repaired it by closing the broken gap (I might have had to add some new plumber’s tape, but I don’t remember) and putting the tension bolt in another place. I added more fastener screws around the collar too:

Guy Wire Stove Pipe Holder Fixed

After that, I realized that the stove pipe was kind of jack-knifing at the pipe joint, and so I loosened the tension on the guy wires, straightened the pipe, and added screws to the pipe joint:

Stove Pipe Connections Fastened by Screws

I then re-tightened the guy wires, re-leveling as I went. There’s a running joke out here about not giving David the level, as I have a tendency to spend too much time getting it exactly correct, and I have had to learn to let go of that some, but….. when it is level, it is niiiiiice! 🙂

More Triple Wall Stove Pipe Leveling

With the triple wall in place, I needed to caulk the collar, using high-temperature, silicon caulking:

High Temperature Caulking Around Stove Pipe Collar

And also caulk the storm collar, slid into position over the collar opening:

High Temperature Caulking Around Stove Pipe Storm Collar

And I caulked the screws into the pipe holding the guy wire collar, just in case:

High Temperature Caulking On Guy Wire Pipe Collar Screws

Finally, here it is, reaching up to the sky!

Triple Wall Stove Pipe to the Sky

Then, it was time to head on inside. I planned to use step stones under the stove, but wanted to put them on a plywood base to hopefully help disperse the stove weight more evenly across the subfloor and double floor joists I put in this area:

Stove Step Stone Plywood in Place

And then I placed the stones:

Stove Step Stones in Place

The stove has been hooked up to a dolly since we moved it into the house, and Sue and I were able to get it to tilt back on the dolly so we could move it. I tried pulling the stove up onto the stones using the dolly, but couldn’t get it to roll up them. Here, Sue is maintaining the lean while I do some prep work:

Holding the Cook Stove on the Dolly

I added 2×4 wood pieces on the far side to keep the stones from sliding, and then made a little ramp, which worked nicely:

Stove Step Stone Ramp

And here it is with the free end resting on wood blocks.

Cook Stove on Stones on Wood Blocks

After doing some quick tilt back and single block removing maneuvers, so the stove wouldn’t come slamming down onto the stones, we needed a way to gently lower it, and we used the car floor jack, which worked great!

Using Car Floor Jack to Lower Stove Side

And here it is in position on the stones!

Wood Burning Cook Stove in Place

Next was the internal stove pipe, which is installed male end on top sliding into the female end below. At first I thought this would be wrong (after I had installed all of the piping!), but after investigating, it is correct — the smoke doesn’t come out the sides and is actually apparently sucked up the pipe with it this way; plus, it keeps the moisture inside the pipe and not dripping down the outside.

Here, I installed the damper in the first piece above the bread warmer of the stove:

Stove Pipe Damper Installed

And here is all of the pipe installed:

Internal Stove Pipe Installed

I used an adjustable section for the top, which slides into the top static piece:

Adjustable Stove Pipe Section Moved into Place

And then adjusts upward around the male end of the starter piece which sticks through the external stove pipe base:

Stove Pipe Adjustable Section Ready

We also received a water warmer for the stove, and here I’ve prepped it with the piping, cap and valve:

Preparing Wood Burning Stove Water Warming Tank

And here it is in place:

Wood Burning Stove Water Warming Tank in Place

And here is our first fire! Apparently, at least the first time, and some say at the beginning of each season, you’re supposed to light three to five light fires, letting it fully cool in between, to season the cast iron of the stove, which apparently can crack if it gets high heat before doing that:

Our First Wood Burning Cook Stove Fire

We look forward to eventually having the community over on cold days for meetings! And to maybe be warm during the really cold days around here. We have used a propane Mr. Heater Buddy since about the beginning in our very un-insulated camper, which has got us by, and we are very thankful for that; but maybe we’ll be a little warmer now. 🙂 And it’s hopefully one further step on getting less world-dependent.

We are very grateful to the Lord for Him allowing us a wood burning cook stove and to be able to have it installed now. And thanks much again to the Folks for this gracious gift, and the continued support from all our parents!

— David

A House – Update XXVII – Library Ceiling & Homestead Painting

Continuing on from our previous community work day, working on the house ceiling, the group once again graciously came to our place to help out on our homestead!

For the guys, it was back into the house to try to finish up as much of the ceiling as possible.

And here are a few pictures of the work:

Putting Up Ceiling Panels in the House Library
Cutting House Library Ceiling Panels

And the final progress! Almost total complete now…just some edge pieces, and I need to figure out an attic access point:

House Library Ceiling Panels Complete
Another View of House Library Ceiling Panels Complete

Community Work Day Homestead Painting

The ladies and children came over too, and graciously helped out in painting just about all of the painted structures we have in our inner field area — goat sheds, chicken tractors and coups, the outhouse, summer kitchen roof fascia, the cistern covering structure, and a generator box. They sanded the wood, and then painted…

And here they are in freeze-frame action!

Still More Goat Shed Painting
Goat Shed Painting
More Goat Shed Painting
Continued Goat Shed Painting
Painting the Cistern Top

Victory over the goat sheds!

Goat Shed Painting Victory!

Painting war paint! (there’s irony in there somewhere 🙂 )

Painting War Paint

And some of the other completed structures:

Painted Mini Chicken Tractor
Painted Outhouse

We’re grateful to the Lord for granting the resources and a serving community of people to help us as we desire and try to live our lives out of love for Christ and love for each other, and thanks very much to the group for all of the help!

— David

A House – Update XXVI – More Great Room Ceiling

I mentioned in our 2014 goat kid blog post that I’ve been busy with seasonal chores, which I hope to write about soon; but they have also kept me from work on the house. Not much has been done since the upper west siding was finished, but on this last “first Wednesday of the month” community work day, which actually ended up being second Wednesday so more folks could participate, the men came over to our place; and we continued putting up ceiling panels!

And so, here are some of the sights of that work….

Here, the guys are finishing screwing in the rough-shod, T-111-like panel. We’re using 1 5/8-inch Deskmate screws:

Screwing in the Ceiling Panel

Then us getting ready for a panel:

Preparing for Ceiling Panel Installation

And placing it. Although they’re lighter than other 4-foot by 8-foot panels, holding them over your head for any length of time gets a bit tiring. 🙂 :

Placing the Ceiling Panel

And holding:

Holding the Ceiling Panel While Installing

Here is the cutting crew…first measuring:

Measuring a Ceiling Panel for Cutting

Then cutting:

Cutting the Ceiling Panel

And here is the west end of the house, with the main panels in place!

West End of Great Room with Main Paneling Done

And here is the east side:

East End of Great Room with Main Paneling Done

And this shows a bit of the library, which is the part that still needs to be done:

The Library Still Needs to be Done

Here are the fellows relaxing at the end of the day:

Relaxing at the End of Community Work Day

We are thankful as always to the Lord for Him granting the resources to work on the ceiling, the safety He granted, able bodies to perform the work, and the community He has allowed us and the opportunity to work together. We always pray He glorifies Himself through these things!